Phase 1:  Data Center Network Hardware Upgrade Plan

As part of the campus network hardware and security upgrade, the network infrastructure team will be replacing Data Center network hardware starting May 30, 2024, and throughout the month of June 2024.  The upgrade plan will end on June 21, 2024.   

To minimize impact on the campus activity, the upgrades are scheduled for 10pm and 2am on Tuesdays and Fridays.  As a result of the upgrade, the campus will benefit from

  • Increased network bandwidth to the Internet and IT resources. 
  • Improved network security with faster connectivity.
  • Simplify the IT infrastructure and consolidate the network resources for better network performance. 

Upgrade Plan and Scheduled

Date Upgrade devices Impact:
Building wired Internet
Impact:
IT and server resource
Impact:
Building Network, and Phone
Impact:
Building wireless Internet
05/31/2024 Campus Cores (Liaison, Core1, Core2) Yes, multiple short intermittent (1-3 minutes) connections Yes, multiple short intermittent (1-3 minutes) connections Yes, multiple short intermittent (1-3 minutes) connections Yes, multiple short intermittent (1-3 minutes) connections
06/04/2024 Wireless Core, Data Center switches No Yes, multiple short intermittent  (1-3 minutes) connections to college servers No Yes, multiple intermittent (3-7 minutes) connections to wireless and Internet
06/07/2024 PLN Data Center  server switches Yes, multiple short intermittent (1-3 minutes) connections Yes, multiple short intermittent (1-3 minutes) connections to IT and college servers Yes, multiple short intermittent (1-3 minutes) connections No
06/11/2024 Modular Data Center server switches No Yes, multiple short intermittent (1-3 minutes) connections to IT and college servers No No
06/14/2024 Modular Data Center server switches Yes, multiple intermittent (3-7 minutes) connections to wireless and Internet Yes, multiple intermittent (3-7 minutes) connections to wireless and Internet Yes, multiple intermittent (3-7 minutes) connections to wireless and Internet No
06/21/2024 Data Center network upgrade final test Yes, multiple short intermittent (1-3 minutes) connections Yes, multiple short intermittent (1-3 minutes) connections Yes, multiple short intermittent (1-3 minutes) connections Yes, multiple short intermittent (1-3 minutes) connections

 

Phase 2:  Building network Hardware Upgrade Plan

Following the Phase 1 plan, the network infrastructure team will replace building network hardware starting June 24, 2024, and throughout July 2024.  The upgrade plan will end on August 9, 2024.   

The upgrade will involve moving the building’s computer, phone, and wireless access point network connection from legacy to new network equipment.  During the upgrade, the cable will be disconnected and moved to new network hardware.  The outage is less than 30 seconds.  We will send the reminder to the user a week before the scheduled upgrade.  

Buildings Number of Telecom Rooms  Migration date
Children Center 3 6/19 (W)
PLN 7 6/24 (M), 6/28 (F)
PLS 7 6/25 (Tu), 6/28 (F)
TSU 7 6/26 (W)
MH 9 6/27 (Th)
Trigen, Power Station 2 6/28 (F)
HUM 9 7/1 (M)
SRC 4 7/1 (M)
SGMH 13 7/2 (Tu)
LH 9 7/8 (M)
VA-A to VA-H 11 7/9 (Tu)
CPAC 8 7/10 (W)
CP 23 7/11 (Th) , 7/12 (F)
KHS 9 7/15 (M)
Sport Complex, Club House 8 7/16 (Tu)
RGC 2 7/16 (Tu)
Student Housing Phase 3 6 7/17 (W)
Student Housing Phase 2 6 7/18 (Th)
Student Health Center (SHCC) 2 7/18 (Th)
Corp Yard (T Building) 11 7/19 (F)
ASC 3 7/22 (M)
Titan Hall 5 7/22 (M)
Arboretum 4 7/23 (Tu)
Parking Structures 6 7/23 - 25 (Tu-Th)
Visitor Center 3 7/24 (Th)
GAH (Alumni House) 1 7/24 (Th)
Bookstore 3 7/26 (F)
UPD 2 7/26 (F)
Carl's 1 7/26 (F)
DBH 4 7/29 (M)
DBH Surge 9 7/29 (M)
CS 5 7/30 (Tu)
Engineer and Engineer Wings 4 7/31 (W)
EC 7 8/1 (Th)
Total Telecom Rooms 226